The Armed Services Board of Contract Appeals (ASBCA) recently
reminded contractors of the importance of documenting submissions
to the government and retaining that documentation. In
Strategic Technology Institute, ASBCA No. 61911 (January
5, 2022), the government asserted a claim disallowing costs in an
incurred cost proposal (ICP) more than six years after the alleged
submission. The contractor was unable to prove it timely submitted
its ICP and therefore lost the benefit of its statute of
limitations defense.
Strategic Technology Institute (STi) received its first cost
reimbursement contract, with the Navy, in 2008. STi retained an
outside accountant to prepare its FY 2008 and 2009 ICPs. After
receiving the final ICPs, STi's Director of Operations directed
an STi employee to load the documents onto CDs for submission to
the government. STi alleged this submission occurred, by either the
Director or the employee, via UPS or FedEx, but retained no
documentation of