ARTICLE · 12 JANUARY 2024

ASBCA Allows Subcontractors' Pandemic-Related Claims To Move Forward

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

On December 20, 2023, the Armed Services Board of Contract Appeals (Board) denied the government's motion to dismiss a prime contractor's pandemic-related claims filed on behalf of its subcontractors.

United StatesGovernment, Public Sector

On December 20, 2023, the Armed Services Board of Contract Appeals (Board) denied the government's motion to dismiss a prime contractor's pandemic-related claims filed on behalf of its subcontractors. The Board rejected the government's arguments that the claims failed to state any claims for relief that could be granted, were barred by the affirmative defense of sovereign acts, and failed to provide separate sums certain for purported sub-claims.

The government awarded the design and construction contract in 2019. After the COVID-19 pandemic began in 2020, the contractor alleged that its subcontractors faced a number of impacts, such as government-ordered changes to the method and manner of the work, restricted access to the worksite, excessive price increases, and supply chain issues. The contractor also alleged that the government did not act in good faith by directing the contractor "to proceed with the Project as if the Project were immune to the pandemic's

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.