On September 23, 2019, the U.S. Court of Appeals for the Ninth
Circuit affirmed the Bureau of Indian Affairs'
("BIA") approval of an industrial-scale wind facility in
Southern California, concluding that the BIA's review of the
project complied with the National Environmental Policy Act
("NEPA") and the Administrative Procedure Act
("APA"). Protect Our Communities Found. v.
LaCounte, 939 F.3d 1029 (9th Cir. 2019).
The wind facility at issue was broken into two phases to address
the fact that some turbines will be located on federal land, while
other turbines will be located on tribal land. Phase I of the
project, involving 65 turbines on federal land, was approved by the
Bureau of Land Management ("BLM"). Phase II of the
project, involving 20 turbines on tribal land, was approved by the
BIA. Both approvals were based on an environmental impact statement
("EIS")—required under NEPA and prepared by
BLM—that covered both phases. Two individuals and an
environmental