ARTICLE · 26 MAY 2021

FERC Announces Greenhouse Gas Emissions Will Be Considered In Review Of Natural Gas Pipeline Certificates

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

he March 22 Order also granted a certificate for Northern to construct and operate new pipeline in order to replace the capacity associated with its abandoned facilities.

United StatesEnvironment

On March 22, 2021, the U.S. Federal Energy Regulatory Commission ("FERC") issued an order authorizing Northern Natural Gas Company ("Northern") to abandon-in-place a segment of its natural gas pipeline running from Nebraska to South Dakota. Northern Natural Gas Co., 174 FERC ¶ 61,189 (2021) (the "March 22 Order"). The March 22 Order also granted a certificate for Northern to construct and operate new pipeline in order to replace the capacity associated with its abandoned facilities. While the outcome of the March 22 Order is mostly inconsequential, the order contains a potentially significant change in how FERC will consider greenhouse gas ("GHG") emissions in its review of natural gas pipeline certificate applications going forward. Specifically, the March 22 Order explains that FERC will now "consider all appropriate evidence regarding the significance of a project's reasonably foreseeable GHG emissions and those emissions' contribution to climate change." This is

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from