ARTICLE · 30 AUGUST 2017

Does NEPA Require Assessment Of Downstream GHG Emissions Resulting From Gas Pipelines?

Last week, a divided panel of the D.C. Circuit Court of Appeals ruled that FERC violated NEPA in failing to assess downstream greenhouse gas emissions resulting from construction of the Sabal Trail pipeline...

United StatesEnvironment

Last week, a divided panel of the D.C. Circuit Court of Appeals ruled that FERC violated NEPA in failing to assess downstream greenhouse gas emissions resulting from construction of the Sabal Trail pipeline, part of the Southeast Market Pipelines Project. If the decision stands, it is going to have a very significant impact on review and development of gas pipelines.

(Full disclosure – Foley Hoag represents NextEra, one of the developers of the project, in a variety of environmental matters, though we were not involved in this case.)

To the majority, the case was fairly straightforward. NEPA requires assessment of indirect impacts of projects, which are those which are downstream of the project, but nonetheless are "reasonably foreseeable." Since the basic purpose of the pipeline is to supply gas to power plants, the Court had no trouble concluding that GHG emissions from those plants are reasonably foreseeable.