IN RECENT YEARS THERE HAS BEEN INCREASED ENVIRONMENTAL
AWARENESS AND A GREATER FOCUS ON SUSTAINABLE AND "GREEN"
ENERGY PRODUCTION IN GCC COUNTRIES. BUDGETARY PRESSURES CAUSED BY
THE RECENT LOW OIL PRICES HAVE LED GCC COUNTRIES TO START
DIVERSIFYING THEIR ENERGY MIXES AWAY FROM HYDROCARBON-DEPENDENT
TECHNOLOGIES AND TOWARDS WASTE TO ENERGY (WTE) PROJECTS TO PROVIDE
A SOLUTION.
THE SHARJAH PROJECT
Masdar and Bee'ah are developing the Sharjah Project on a
50/50 basis, with Bee'ah supplying municipal solid waste (MSW)
and Sharjah Electricity and Water Authority (SEWA) purchasing the
power produced.
The Sharjah Project will be located adjacent to Bee'ah's
existing landfill site in Sharjah and, once completed in 2020, will
incinerate approximately 300,000 tonnes of MSW and displace almost
450,000 tonnes of CO2 emissions per year. It will contribute to
Sharjah's effort to reach its "zero
waste-to-landfill" target by 2020 and the UAE's goal of
diverting 75% of MSW from