On January 5, 2021, the U.S. Army Corps of Engineers (the Corps)
released the
final version of a rule revamping certain nationwide permits
(NWPs) under the Clean Water Act (CWA). The CWA authorizes the
Corps to issue general permits authorizing categories of activities
that have minimal individual and cumulative adverse environmental
effects. These permits remain in effect for no more than five
years, at which point the Corps must renew the permits.
This rule reissues and modifies 12 nationwide permits (NWPs) and
issues four new NWPs. Of these
16 NWPs, the most impactful changes are to NWP 12.
NWP 12 controversy
Until this new rule, NWP 12 applied to "activities required
for the construction, maintenance, repair, and removal of utility
lines and associated facilities in waters of the United
States." The Permit defined a "utility line" as
"any pipe or pipeline for the transportation of any gaseous,
liquid, liquescent, or slurry substance for any purpose, and