ARTICLE · 26 MARCH 2024

Third Circuit Victory Marks Precedent For How The Filed Rate Doctrine Applies To Auctions

Jenner & Block LLP
Jenner & Block LLP
Contributor
Jenner & Block LLP

Jenner & Block LLP

Jenner & Block’s London office has built a powerful reputation for representing clients in their...

View firm profile
Explore more from Jenner & Block LLP

The Third Circuit agreed with our argument that the Federal Energy Regulatory Commission cannot retroactively change the rules of an electric capacity auction after those rules have been applied.

United StatesEnergy and Natural Resources
Jenner & Block
Jenner & Block

The Third Circuit agreed with our argument that the Federal Energy Regulatory Commission cannot retroactively change the rules of an electric capacity auction after those rules have been applied. The victory represents a precedential ruling about how the filed rate doctrine applies to such auctions.

Auction rules produce the ultimate rates set, and the filed rate doctrine forbids retroactive changes. But in this case, the grid operator that held the auction, PJM Interconnection, LLC, discovered after accepting bids that applying its auction rules would produce a cost increase for some customers. PJM delayed announcing results, and sought FERC's approval to retroactively amend the rules to produce a different result. In 2023, FERC approved PJM's change, ruling that the auction results had not officially been announced, so its approval did not violate the filed rate doctrine.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from