Third Circuit Upholds FERC Jurisdiction Over Regional Transmission Planning In PJM Dispute

The U.S. Court of Appeals for the Third Circuit issued a precedential decision in Transource Pennsylvania LLC v. Pennsylvania Public Utility Commission (Transource)...

United StatesEnergy and Natural Resources

The U.S. Court of Appeals for the Third Circuit issued a precedential decision in Transource Pennsylvania LLC v. Pennsylvania Public Utility Commission (Transource) on Sept. 5, 2025. The Third Circuit affirmed a district court ruling that the Supremacy Clause of the U.S. Constitution preempts the Pennsylvania Public Utility Commission's (PAPUC) denial of siting applications for a regional transmission project previously approved by PJM Interconnection LLC (PJM), a regional transmission organization regulated by the Federal Energy Regulatory Commission (FERC).

The case arose from PJM's selection of Transource's Project 9A to alleviate congestion on the AP South Reactive Interface, a transmission bottleneck affecting electricity prices in Maryland, Virginia and the District of Columbia. PJM approved the project using its FERC-approved benefit-cost methodology, which evaluates regional transmission needs and economic efficiency. Despite PJM's approval, the PAPUC

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from