In one of the first rulings applying Loper Bright Enterprises v. Raimondo, the Supreme Court on Tuesday vacated and remanded the D.C. Circuit's decision in Solar Energy Industries Association v. FERC for further consideration

United StatesEnergy and Natural Resources

In one of the first rulings applying Loper Bright Enterprises v. Raimondo, the Supreme Court on Tuesday vacated and remanded the D.C. Circuit's decision in Solar Energy Industries Association v. FERC for further consideration.

The case, otherwise known as Broadview Solar, involves the Federal Energy Regulatory Commission's ("FERC") interpretation of "qualifying facility" ("QF") under the Public Utility Regulatory Policies Act of 1978 ("PURPA"). While PURPA permits certain renewable energy generators with a power production capacity of 80 MW or less to qualify for benefits, such as an exemption from certain filing obligations and a requirement that electric utilities must purchase their output in non-RTO regions, the Commission concluded in Broadview Solar that a solar and battery facility with a 160 MW gross capacity was nonetheless a QF under PURPA because the project was physically limited to providing 80 MW of power to the grid at any given time.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from