ARTICLE · 07 JULY 2009

Supreme Court Establishes Boundaries Between Wetlands And Pollution Discharge Programs Under The Clean Water Act

The Supreme Court issued its much anticipated decision this week addressing the jurisdictional boundaries between the U.S. Army Corps of Engineers ("Corps") and U.S. Environmental Protection Agency ("EPA") in permitting activities that may constitute both a wetlands fill and a pollution discharge under the Clean Water Act ("CWA").

United StatesEnergy and Natural Resources

The Supreme Court issued its much anticipated decision this week addressing the jurisdictional boundaries between the U.S. Army Corps of Engineers ("Corps") and U.S. Environmental Protection Agency ("EPA") in permitting activities that may constitute both a wetlands fill and a pollution discharge under the Clean Water Act ("CWA"). 

In Coeur Alaska, Inc. v. Southeast Alaska Conservation Council, Nos. 07-984 and 07-990 (June 22, 2009), the Court held that the Corps properly exercised its wetlands permitting jurisdiction where the relevant activity—here, a mine slurry discharge to a navigable lake—met the Corps' regulatory definition of wetlands fill material and was therefore exempt from regulation by EPA under the National Pollution Discharge Elimination System ("NPDES") program.  The decision provides greater clarity for entities engaged in potentially "mixed" discharge activities but may foreshadow greater EPA involvement in reviewing Corps wetland permitting

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from