ARTICLE · 06 JULY 2016

Responsible Party Under OPA Not Responsible For Damages Resulting From Government Imposed Moratorium And Permitorium

Judge Barbier found Plaintiffs had failed to sustain their burden of plausibly alleging claims which satisfied OPA's causation standard, and thus granted BP's Motion to Dismiss.

United StatesEnergy and Natural Resources

Case:   In re: Oil Spill by the Oil Rig “Deepwater Horizon” in the Gulf of Mexico, on April 20, 2010
             United States District Court for the Eastern District of Louisiana
             No. 2:10-md-02179

Appeal:    In Re: Deepwater Horizon
                United States Court of Appeals for the Fifth Circuit
                No. 16-30245

Adding to the wealth of case law stemming from the DEEPWATER HORIZON/Macondo spill, Judge Carl J. Barbier refused to impose liability on BP for the economic losses sustained by various oil industry-related businesses due to the U.S. Government imposed 6-month moratorium on both continuing ongoing activity on 33 deepwater wells being drilled (deepwater being defined as more than 500 feet of water) and on granting of permits for new wells being drilled using floating rigs.