ARTICLE · 11 OCTOBER 2021

Religious Freedom Restoration Act Claims Against FERC-regulated Pipeline Must Be Presented Initially To FERC, Regardless Of Damages Sought

Relying on a 2018 decision from the United States Court of Appeals for the Third Circuit, a Pennsylvania district court reaffirmed that Religious Freedom Restoration Act (RFRA)...

United StatesEnergy and Natural Resources

Relying on a 2018 decision from the United States Court of Appeals for the Third Circuit, a Pennsylvania district court reaffirmed that Religious Freedom Restoration Act (RFRA) claims against a Federal Energy Regulatory Commission (FERC)-regulated pipeline must be made initially to FERC. Adorers of the Blood of Christ v. Transco. Gas Pipe Line Co.

Interplay between FERC and RFRA

The plaintiff religious organization claimed FERC's approval of a pipeline through its property violated RFRA, entitling plaintiff to monetary damages. But the plaintiff failed to raise the RFRA claim in the FERC proceedings that authorized the pipeline path (and failed to participate in any way in the FERC proceedings). Thus, the defendant sought to dismiss the case, claiming the district court did not have jurisdiction to hear the matter.