Purely Financial Traders Not Liable for RSG Charges in Midwest ISO Market

On Thursday, October 26, 2006, the Federal Energy Regulatory Commission (“FERC”) issued an order on rehearing clarifying its prior determination that virtual transactions in the electricity markets operated by the Midwestern Independent Transmission System Operator, Inc. (“MISO”) were required to be assessed revenue sufficiency guarantee (“RSG”) charges.

United StatesEnergy and Natural Resources
Paul Turner
Paul Turner

Originally published November 1, 2006

On Thursday, October 26, 2006, the Federal Energy Regulatory Commission ("FERC") issued an order on rehearing clarifying its prior determination that virtual transactions in the electricity markets operated by the Midwestern Independent Transmission System Operator, Inc. ("MISO") were required to be assessed revenue sufficiency guarantee ("RSG") charges.1 On April 25, 2006, FERC had issued an order indicating that virtual traders may be assessed RSG charges, potentially even for prior periods. That order had caused some confusion and uncertainty in the MISO markets. Since April, day-ahead and real-time prices diverged, and at least one hedge fund announced it would exit the market because of such uncertainty. As a result of this latest order, however, purely financial traders that transacted in the MISO virtual markets, but did not physically withdraw energy in real time, will not be assessed any RSG charges — neither retroactively for any prior

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from