On October 4, 2019, the U.S. Supreme Court agreed to review the
4th Circuit's rejection of the National Forest Service's
permit authorizing the Atlantic Coast Pipeline (ACP) to cross the
Appalachian Trail within the George Washington National Forest.
Although the Mineral Leasing Act (MLA) permits the National
Forest Service, and other agencies, the authority to grant
right-of-ways across federal lands, the 4th Circuit concluded that
the Appalachian Trail, which is managed by the National Park
Service (NPS), was an exempted National Park. Thus, the National
Forest Service's permit, granting a right-of-way, was
determined to be invalid. The decision, if upheld, would force
developers to receive Congressional approval, among other
approvals, before the ACP can proceed with the current route.