NYISO Order No. 2023 Compliance Update: Summary Of November 3 Partial Compliance Filing And Summary Of November 2 Interconnection Issues Task Force Meeting

This post is the second in our ongoing series following the NYISO's compliance with FERC Order No. 2023. In today's post, we cover the NYISO's November 3, 2023...

United StatesEnergy and Natural Resources

This post is the second in our ongoing series following the NYISO's compliance with FERC Order No. 2023. In today's post, we cover the NYISO's November 3, 2023 partial compliance filing made with FERC, as well as provide an update on the November 2 Interconnection Issues Task Force ("IITF") Meeting.

Partial Compliance Filing

On November 3, the NYISO made a partial compliance filing with FERC to begin to transition to the new cluster study interconnection process established by Order No. 2023 ("Filing"). The Filing is intended to allow the NYISO to wind up its current interconnection process to allow it to devote all resources to the new cluster study process. Specifically, the Filing seeks to eliminate the Detailed Optional Feasibility Study and System Reliability Impact Study ("SRIS") currently offered by the NYISO as of November 30, 2023 as these studies will no longer be needed in the new interconnection process. For projects that are already in

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from