NY Court Upholds NY Public Service Commission's Grant Of Permit To South Fork Wind

South Fork Wind's 7.6-mile New York State transmission line has been contentious since the project's inception around 2017...

United StatesEnergy and Natural Resources

Last week, actions by the Second Department of the New York State Supreme Court Appellate Division set the tone for offshore wind development in New York by denying a challenge brought by local opponents to the NY Public Service Commission's ("NYPSC") grant of a Certificate of Environmental Compatibility and Public Need ("CECPN") for the transmission line needed to interconnect New York State's first offshore wind project, South Fork Wind, to the mainland grid. As many have turned to the courts to try to delay or prevent renewable energy projects of all types, this decision will help clear the path for not only New York's offshore wind industry, but for other renewable energy projects as well.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.