ARTICLE · 13 JANUARY 2010
Nuclear Utility Awarded More Than $50 Million For Partial Breach Of Contract Claim
Perkins Coie LLP
On December 18, 2009, the U.S. Court of Federal Claims issued an opinion awarding more than $50 million to Perkins Coie's client, Wisconsin Electric Power Company (WE), in its claim against the U.S. Department of Energy (DOE) for the partial breach of a contract to accept and dispose of spent nuclear fuel (SNF) and high-level waste (HLW) from WE's Point Beach Nuclear Power Plant.