Nuclear Utility Awarded More Than $50 Million For Partial Breach Of Contract Claim

On December 18, 2009, the U.S. Court of Federal Claims issued an opinion awarding more than $50 million to Perkins Coie's client, Wisconsin Electric Power Company (WE), in its claim against the U.S. Department of Energy (DOE) for the partial breach of a contract to accept and dispose of spent nuclear fuel (SNF) and high-level waste (HLW) from WE's Point Beach Nuclear Power Plant.

United StatesEnergy and Natural Resources

On December 18, 2009, the U.S. Court of Federal Claims issued an opinion awarding more than $50 million to Perkins Coie's client, Wisconsin Electric Power Company (WE), in its claim against the U.S. Department of Energy (DOE) for the partial breach of a contract to accept and dispose of spent nuclear fuel (SNF) and high-level waste (HLW) from WE's Point Beach Nuclear Power Plant. See http://www.uscfc.uscourts.gov/opinions_decisions_general/Published (http://tinyurl.com/yz7z8zw)

The WE litigation is one of numerous lawsuits filed by utilities against the DOE for its failure to begin accepting and disposing the utilities' SNF/HLW by January 31, 1998, as required by the Nuclear Waste Policy Act (NWPA), 42 U.S.C. §§ 10101-10270, and the standard contracts that the NWPA required the utilities to enter into with DOE.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from