Ninth Circuit Holds Utilities Are Ineligible For RTO Membership Adder When Membership Is Involuntary

On January 8, 2018, the U.S. Court of Appeals for the Ninth Circuit ("Ninth Circuit") ruled that FERC acted arbitrarily and capriciously in approving a 50 basis-point incentive ...

United StatesEnergy and Natural Resources

On January 8, 2018, the U.S. Court of Appeals for the Ninth Circuit ("Ninth Circuit") ruled that FERC acted arbitrarily and capriciously in approving a 50 basis-point incentive adder to Pacific Gas & Electric Company's ("PG&E") return on equity ("ROE") for its participation in the California Independent System Operator Corporation ("CAISO"). In particular, the Ninth Circuit held that FERC did not follow its precedent by approving PG&E's incentive adder while dismissing arguments that PG&E's ongoing membership in CAISO was required by a California Public Utilities Commission ("CPUC") order and thus was not voluntary.

In 2006, FERC issued Order No. 679, which approved an incentive adder of 50 basis-points to a transmission owner's ROE for joining or continuing to participate in a regional transmission organization/independent system operator ("RTO/ISO"). In creating this incentive adder, FERC reasoned that inducing transmission owners to become members in RTOs/ISOs

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from