On May 24, 2005, the United States Court of Appeals for the Ninth Circuit held in Industrial Customers of Northwest Utilities v. Bonneville Power Administration that a determination by the Bonneville Power Administration to trigger a rate adjustment clause was not a final agency action subject to judicial review.

United StatesEnergy and Natural Resources

On May 24, 2005, the United States Court of Appeals for the Ninth Circuit held in Industrial Customers of Northwest Utilities v. Bonneville Power Administration that a determination by the Bonneville Power Administration ("BPA") to trigger a rate adjustment clause was not a final agency action subject to judicial review.

The BPA is a federal agency within the United States Department of Energy. It has marketing authority over nearly all the electric power generated by federal facilities in the Northwest, and is also charged with oversight of the federal high-voltage transmission system used to deliver that power, as well as non-federal power, to its customers. The BPA establishes its own power rates, subject to approval by the Federal Energy Regulatory Commission ("FERC"). At issue in Industrial Customers were the BPA wholesale power rates which were subject to a Safety-Net Cost Recovery Adjustment Clause. Upon the occurrence of one of two conditions, the Adjustment Clause allowed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.