Share on LinkedInShare on LinkedIn

ARTICLE · 17 JUNE 2013

New PA Court Decision Adds To Case Law On ‘Commencing A Well’

A Pennsylvania district court recently held that a gas and oil lease was extended beyond the primary term where the lessee had commenced construction of a well and thereafter began drilling with due diligence, regardless of the fact that no well was actually completed or in production at the time the primary term expired.

United StatesEnergy and Natural Resources

A Pennsylvania district court recently held that a gas and oil lease was extended beyond the primary term where the lessee had commenced construction of a well and thereafter began drilling with due diligence, regardless of the fact that no well was actually completed or in production at the time the primary term expired.  Good Will Hunting Club, Inc. v. Range Resources–Appalachia, LLC, No. 4:11-CV-1152, 2013 WL 2297170 (M.D. Pa. May 24, 2013).

The lease at issue in Good Will was, as the Court noted, ambiguous and had conflicting provisions regarding expiration.  In one section the lease contained a standard hold-by-production clause.  However, a later section provided that the lease could be held so long as the lessee "commence[d]" a well within the primary term and drilled the well "with due diligence."  To resolve this facial ambiguity, the Court looked to the intent of the parties at the time of drafting.  In doing so, the Court imputed to the Good Will Hunting

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from