NERC Files Responses To CIP Version 4 Survey Questions, Identifies Likely Number Of Critical Assets

On June 30, 2011, NERC filed its remaining responses to FERC’s recent questions on the expected scope of bulk-power system facilities considered Critical Assets under the proposed CIP-002-4 Reliability Standard.

United StatesEnergy and Natural Resources
Morgan, Lewis & Bockius LLP'S FERC Energy Practice
Morgan, Lewis & Bockius LLP'S FERC Energy Practice

On June 30, 2011, NERC filed its remaining responses to FERC's recent questions on the expected scope of bulk-power system facilities considered Critical Assets under the proposed CIP-002-4 Reliability Standard. The proposed standard would, for the first time, create bright-line criteria for identifying the facilities subject to NERC's CIP-002 through CIP-009 Critical Infrastructure Protection Reliability Standards, moving away from the current criteria that grant a great deal of discretion to individual entities.

As explained by NERC, the survey results suggest that the implementation of the bright-line criteria in CIP-002-4 will substantially increase the number of Critical Assets with Critical Cyber Assets.