ARTICLE · 18 MARCH 2026

Massachusetts AGO Rejects Yet Another Municipal Solar And Battery Storage Moratorium

On March 11, 2026, the Massachusetts Attorney General's Office ("AGO") disapproved a proposed temporary zoning moratorium on large-scale solar installations...

United StatesEnergy and Natural Resources

On March 11, 2026, the Massachusetts Attorney General's Office ("AGO") disapproved a proposed temporary zoning moratorium on large-scale solar installations and battery energy storage systems ("BESS") in the Town of Blandford. The decision is the latest in a growing line of AGO disapprovals of municipal bylaws that frustrate state law on the siting of solar and BESS facilities. The decision also offers a particularly thorough explanation of why such moratoria run afoul of the state zoning act, G.L. c. 40A.

Blandford's Zoning Moratorium Proposal

Blandford proposed amending its zoning bylaws to prohibit the use of land or structures for large-scale solar installations and BESS through May 31, 2026, or until the Town adopted amended zoning bylaws, whichever occurred earlier. The town cited several justifications for the bylaw: three approved installations already completed or under construction, two more in permitting, and three additional projects expressing interest. Because solar

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from