The IRS recently released Notice 2014-46 (the Notice) which provides
welcome guidance to tax equity investors and developers on the
construction of wind, geothermal, biomass, landfill gas and certain
hydropower and marine hydrokinetic energy projects for purposes of
qualifying for the section 45 renewable electricity production tax
credit (PTC), or the section 48 investment tax credit (ITC) in lieu
of the PTC.
For these types of projects, in order to take advantage of the
PTC or ITC, construction of the facility must have begun prior to
January 1, 2014. As provided in earlier guidance released by the
IRS (Notice 2013-29), taxpayers may demonstrate that
they started construction timely either by beginning physical
construction of a significant nature (the Physical Work Test) or
incurring at least 5% of the total costs of the eligible property
(the 5% Safe Harbor). In all cases, taxpayers must make continuous
progress toward completion of the facility once construction