Great Lakes Offshore Wind Icebreaker Project Conditionally Approved By Ohio Power Siting Board Staff

Mayer Brown
Mayer Brown
Contributor
Mayer Brown

Mayer Brown

Mayer Brown is a leading international law firm positioned to represent the world’s major...

View firm profile
Explore more from Mayer Brown

On July 3, 2018, the Staff of the Ohio Power Siting Board issued its Report of Investigation and recommended that the Board approve the six-turbine, $126 million Icebreaker project...

United StatesEnergy and Natural Resources

On July 3, 2018, the Staff of the Ohio Power Siting Board (Board) issued its Report of Investigation and recommended that the Board approve the six-turbine, $126 million Icebreaker project being developed by Icebreaker Windpower, Inc. (Applicant and successor to Lake Erie Energy Development Corp.), subject to at least 34 separate conditions. Notably, several of these conditions will require:

  1. additional proceedings, including a new proceeding for the related 138 kV transmission interconnection, which the Staff found a major utility facility, pursuant to the definition of that term provided in R.C. 4906.01;
  2. a modified submerged lands lease (SLL) to reflect the "modest" project changes since the 2014 execution of the current SLL;