Georgia Public Service Commission Approves Georgia Power's Major Generation Expansion To Support Data Center Load

Georgia Power's 2025 IRP, filed in January and approved in July 2025, projects extraordinary electric demand growth over the next decade, driven largely by data center expansion.

United StatesEnergy and Natural Resources

Key Takeaways

  • The Georgia Public Service Commission (PSC) has unanimously approved Georgia Power Company's (Georgia Power) plan to add nearly 9,885 MW of new generation capacity, primarily to meet projected demand from data centers and other large loads.1
  • The proposed build-out is one of the largest electric generation expansions in the United States.
  • Construction is estimated at $16.5 billion, although customers could pay $50-60 billion over decades.
  • The approval follows months of contested proceedings, expert testimony, and technical filings in PSC dockets concerning the utility's long-term Integrated Resource Plan (IRP) and related certification requests.
  • This approval, formalized through a negotiated stipulation, reflects a regulatory willingness to support significant capacity buildouts while embedding conditions intended to mitigate risks and protect ratepayers.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from