Force Majeure Clauses In Natural Gas Contracts: Fifth Circuit Provides Guidance

The U.S. Court of Appeals for the Fifth Circuit issued a decision on July 16, 2024, in Mieco LLC v. Pioneer Natural Resources USA Inc...

United StatesEnergy and Natural Resources

The U.S. Court of Appeals for the Fifth Circuit issued a decision on July 16, 2024, in Mieco LLC v. Pioneer Natural Resources USA Inc., addressing the interpretation of force majeure clauses under New York law. The case, which arose from Pioneer Natural Resources' inability to deliver contracted natural gas during Winter Storm Uri in 2021, provides critical guidance for parties negotiating and enforcing energy contracts.

The dispute arose when Pioneer invoked a force majeure clause to excuse its failure to deliver contracted amounts of natural gas to Mieco LLC. The storm significantly disrupted gas production in the Permian Basin, forcing Pioneer to halt deliveries and leaving Mieco to purchase replacement gas on the spot market at a cost of approximately $9 million. Mieco then sued Pioneer for breach of contract, challenging the force majeure claim and alleging that Pioneer failed to meet its contractual obligations.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from