Force Majeure Clause Fails To Protect Oil And Gas Lessee From Mistakenly-Scheduled Deadline

In Point Energy Partners Permian, LLC v. MRC Permian Company, — S.W.3d —, No. 21-0461, 2023 WL 3028100 (Tex. 2023)...

United StatesEnergy and Natural Resources

In Point Energy Partners Permian, LLC v. MRC Permian Company, — S.W.3d —, No. 21-0461, 2023 WL 3028100 (Tex. 2023), the Texas Supreme Court held that the lessee could not invoke a force majeure clause to save its oil and gas leases when it inadvertently scheduled its operations to begin after the requisite deadline.

The lessee, MRC Permian Company, received four identical oil and gas leases from certain lessors in 2014. The leases obligated MRC to spud a new well every 180 days after the spud date of the last well during the leases' secondary terms to avoid having the non-developed portions of the leases terminate. In compliance with that obligation, MRC created a drilling schedule listing June 2, 2017 as the spud date of a new well based on its belief that the deadline to spud that well was June 19, 2017. The actual deadline, however, was May 21, 2017.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from