On February 9, 2015, FERC approved the Midcontinent Independent
System Operator, Inc.'s ("MISO") request for a
temporary waiver of its $1,000/MWh energy offer price cap.
FERC's approval will now allow generators with actual,
verifiable costs above the $1,000/MWh energy offer price cap to
receive make-whole payments by increasing the "No Load"
component of their offer after consultation with MISO's
Independent Market Monitor ("IMM"). The waiver of
the energy offer price cap runs from December 20, 2014 to April 30,
2015.
In requesting the waiver, MISO stated that the natural gas price
spikes during the 2013/2014 winter season resulted in MISO
generators experiencing economic restraints when they were not able
to offer output at its true incremental cost. MISO added that
as a result of those constraints and the potential for similar
price spikes during the 2014/2015 winter season, it requested
waiver of the energy offer price cap so that generators could
recover all