FERC Staff Inquiry Concludes No Withholding Of Natural Gas Pipeline Capacity In New England

On February 27, 2018, FERC staff completed an inquiry in which they did not uncover any evidence of anticompetitive withholding of natural gas pipeline capacity on Algonquin Gas Transmission...

United StatesEnergy and Natural Resources

On February 27, 2018, FERC staff completed an inquiry in which they did not uncover any evidence of anticompetitive withholding of natural gas pipeline capacity on Algonquin Gas Transmission, LLC pipeline ("Algonquin") by New England shippers.  The inquiry initially arose from allegations made by the Environmental Defense Fund ("EDF") that Eversource Energy ("Eversource") and Avangrid, Inc. ("Avangrid") were artificially constraining capacity on the Algonquin.  After finding that Eversource and Avangrid did not engage in anticompetitive behavior, FERC staff will not take any further action on the matter.

In November 2017, twelve New England electricity consumers filed a class action lawsuit in in the U.S. District Court of Massachusetts against Eversource and Avangrid, arguing that the energy companies raised power prices by artificially constraining capacity on Algonquin (see December 12, 2017 edition of the

In December 2017, in response to these allegations,