ARTICLE · 02 APRIL 2015

FERC Rule Gives Gen-Tie Owners Safe Harbor From Third-Party Transmission Requests

On March 19, 2015, FERC issued Order No. 807, a rule that makes it easier for developers of non-utility transmission lines that connect power projects to the grid to avoid having to offer unused capacity on those lines to third parties.

United StatesEnergy and Natural Resources

On March 19, 2015, the Federal Energy Regulatory Commission (FERC) issued Order No. 807, a rule that makes it easier for developers of non-utility transmission lines that connect power projects to the grid to avoid having to offer unused capacity on those lines to third parties. The rule also waives open-access transmission related obligations that otherwise apply to transmission owners. When generation developers build new power plants, they ordinarily construct and own new interconnecting power lines – called "gen-tie lines" – and related equipment, such as substations, referred to as "Interconnection Customer's Interconnection Facilities" (ICIF) in FERC parlance. In many instances, these gen-tie lines are a few hundred feet, but for solar, wind and geothermal plants, which are often located in less populated areas, they can extend dozens or even hundreds of miles.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from