FERC Revises Policy On Authorizing Pipelines To Commence Construction Pending Requests For Rehearing Of Certificate Orders

On May 4, 2021, FERC issued Order No. 871-B, clarifying that the rule established in Order No. 871, which precludes FERC from authorizing natural gas pipeline companies to proceed with construction...

United StatesEnergy and Natural Resources

On May 4, 2021, FERC issued Order No. 871-B, clarifying that the rule established in Order No. 871, which precludes FERC from authorizing natural gas pipeline companies to proceed with construction of approved pipeline projects, only applies until the earlier of either (a) the date that a qualifying rehearing request is no longer pending before FERC or (b) 90 days following the date that a qualifying request for rehearing may be deemed denied by operation of law. FERC also limited the application of this rule to requests for rehearing that raise issues reflecting opposition to project construction, operation, or need. Finally, FERC announced a general policy to stay Natural Gas Act ("NGA") section 7 certificate orders during the rehearing period and pending resolution of any timely requests for rehearing. Commissioner James Danly dissented, arguing that the need for Order No. 871 is obviated by further developments on appeal of FERC's practice of indefinite tolling

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from