ARTICLE · 22 OCTOBER 2016
FERC Requires MISO To Apply Its M2 Milestone Payment To All Interconnection Customers, Including External Generators
Troutman Pepper Locke LLP
On October 13, 2016, FERC found that the M2 Milestone Payment in the Midcontinent Independent System Operator, Inc. ("MISO") interconnection process should apply to all interconnection customers, including generators external to MISO that want to participate in MISO's capacity and energy markets through network resource interconnection service