ARTICLE · 19 SEPTEMBER 2017

FERC Rejects Revisions To MISO's Generator Interconnection Review Process Due To Lack Of Justification

On September 7, 2017, FERC rejected, without prejudice, Midcontinent Independent System Operator, Inc.'s ("MISO") proposed tariff revisions regarding its generator interconnection process.

United StatesEnergy and Natural Resources

On September 7, 2017, FERC rejected, without prejudice, Midcontinent Independent System Operator, Inc.'s ("MISO") proposed tariff revisions regarding its generator interconnection process.  FERC found that MISO did not provide sufficient support in its filing to demonstrate that the reductions for its study procedures timeline are just and reasonable.

In October 2016, MISO submitted a proposed restructuring of the timeline for an interconnection customer's Generator Interconnection Agreement.  Rather than a 180-day timeframe, MISO proposed an overall 460-day review timeline, divided over three Definitive Planning Phases ("DPPs").  MISO indicated that the new 460-day timeline reflected the minimum processing time needed for MISO to conduct mandatory studies and make decisions before extending interconnection customers a Generator Interconnection Agreement.  On January 3, FERC accepted MISO's 460-day queue reform, finding overall benefit in preventing ad hoc restudies

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from