Share on LinkedInShare on LinkedIn

ARTICLE · 17 JULY 2018

FERC Rejects PJM's Proposed Tariff Revisions And Initiates Section 206 Proceeding

On June 29, 2018, FERC rejected proposals by Calpine Corporation ("Calpine") and PJM Interconnection, L.L.C. ("PJM") ...

United StatesEnergy and Natural Resources

On June 29, 2018, FERC rejected proposals by Calpine Corporation ("Calpine") and PJM Interconnection, L.L.C. ("PJM") to address what they view as shortcomings in PJM's capacity markets resulting from what they characterize as state subsidy programs that suppress capacity prices (the "June 29 Order").

The June 29 Order is the result of two proceedings initiated in response to increased out-of-market support for particular electric generating resources, including zero emission credits ("ZECs") for nuclear facilities, offshore wind procurements, and more stringent renewable portfolio standards. The first is a March 2016 complaint filed by Calpine and other generation entities pursuant to section 206 of the Federal Power Act alleging that PJM's Tariff—specifically, the Tariff's Minimum Offer Price Rule ("MOPR")—is unjust and unreasonable because it fails to address the impact of subsidized resources on the capacity market. Calpine's complaint expressed concern that the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.