FERC Rejects PJM’s Proposal To Preserve Demand Response Should SCOTUS Uphold Vacating Of Order No. 745

On March 31, 2015, the Commission denied a proposal from PJM Interconnection, LLC ("PJM") to modify the manner in which demand response resources participate in capacity auctions within the RTO.

United StatesEnergy and Natural Resources

On March 31, 2015, the Commission denied a proposal from PJM Interconnection, LLC ("PJM") to modify the manner in which demand response resources participate in capacity auctions within the RTO.  PJM's proposal was intended as a means of maintaining the participation of demand response resources in PJM's capacity market in the event that the U.S. Supreme Court upholds the D.C. Circuit's May 2014 ruling vacating Order No. 745 (see May 27, 2014 edition of the WER).

PJM operates its Reliability Pricing Model ("RPM") capacity market in order to procure sufficient capacity to meet its reliability needs.  Currently, demand response resources participate as a source of supply in the PJM capacity procurement process, and the RPM provides capacity compensation for demand response resources that clear in RPM auctions on the same basis as cleared generation resources.  According to PJM, these demand response resources are currently composed primarily of retail end-users

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from