Share on LinkedInShare on LinkedIn

ARTICLE · 06 JANUARY 2016

FERC Rejects NYISO's Proposed Revisions to Its Public Policy Transmission Planning Process

On December 23, 2015, FERC rejected the New York Independent System Operator, Inc.'s proposed revisions to the Public Policy Transmission Planning Process portion of its Comprehensive System Planning Process...

United StatesEnergy and Natural Resources

On December 23, 2015, FERC rejected the New York Independent System Operator, Inc.'s ("NYISO") proposed revisions to the Public Policy Transmission Planning Process ("Public Policy Process") portion of its Comprehensive System Planning Process ("CSPP") reflected in Attachment Y of its Open Access Transmission Tariff ("OATT"). In rejecting the proposal, FERC found that NYISO proposed tariff revisions that would subject nonincumbent transmission developers to an interconnection process with different requirements than those applied to incumbent Transmission Owners.

On June 29, 2015, NYISO filed proposed revisions to its Public Policy Process. NYISO stated that its tariff revisions would require that a transmission developer submit, as applicable, a valid Interconnection Request for a project under Attachment X of its OATT or a Study Request for the project pursuant to sections 3.7.1 or 4.5.1 of the OATT. On August 28, 2015, FERC staff issued a deficiency letter

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from