FERC Rejects Local Balancing Authority Proposed Cost Recovery Under MISO Tariff

Going forward, Louisiana Generating may resubmit its request for cost recovery in accordance with FERC's explicit expectations set forth in the order.

United StatesEnergy and Natural Resources

On January 12, 2016, the Federal Energy Regulatory Commission ("FERC") issued an order rejecting without prejudice Louisiana Generating LLC's ("Louisiana Generating") request to recover costs associated with performing its obligations as a local balancing authority ("LBA") under the Midcontinent Independent System Operator, Inc's ("MISO")  Open Access Transmission, Energy and Operating Reserve Markets Tariff ("Tariff") Schedule 24 and Schedule 24-A. Going forward, Louisiana Generating may resubmit its request for cost recovery in accordance with FERC's explicit expectations set forth in the order.

As FERC explained in its order, Louisiana Generating is a signatory to the MISO Balancing Authority Agreement ("MISO BA Agreement"), which delineates balancing authority responsibilities between MISO and the LBAs within MISO. Pursuant to MISO Tariff Schedule 24, a signatory to the MISO BA Agreement is eligible to recover the costs incurred as a result of fulfilling its LBA

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from