On September 1, 2017, FERC rejected without prejudice the California Independent System Operator Corporation's ("CAISO") April 18...

United StatesEnergy and Natural Resources

On September 1, 2017, FERC rejected without prejudice the California Independent System Operator Corporation's ("CAISO") April 18, 2017 proposal to revise the CAISO Tariff to create a new class of participating transmission owner ("PTO") called the "Certified Small PTO," whose low-voltage, generator-interconnection-driven network upgrade costs would be allocated regionally, rather than locally.

The CAISO transmission system consists of four load-serving PTOs, each of which assesses "local transmission access" charges on its respective load customers.  These charges recover costs associated with network upgrades to low-voltage transmission facilities (below 200 kV) on the CAISO system.  In contrast, for high-voltage network upgrades, costs are recovered through a "regional transmission access" charge paid by utility distribution companies and metered subsystem operators based on gross load in their service areas.  Three of the four load-serving PTOs are the large

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from