FERC Reaffirms Current MISO Resource Adequacy Program, Cites Recent D.C. Circuit Decision In Separate Rejection Of Other Resource Adequacy Proposals On Remand

In dual orders issued on February 28, 2018, FERC affirmed that the current resource adequacy requirements of the Midcontinent Independent System Operator, Inc. ("MISO") ...

United StatesEnergy and Natural Resources

In dual orders issued on February 28, 2018, FERC affirmed that the current resource adequacy requirements of the Midcontinent Independent System Operator, Inc. ("MISO") remain just and reasonable, and simultaneously rejected an earlier MISO filing that would have imposed additional resource adequacy program changes. The rejection of MISO's earlier filing came after the United States Court of Appeals for the D.C. Circuit ("D.C. Circuit") granted FERC a voluntary remand to reconsider its previous conditional acceptance in light of NRG Power Marketing, LLC. v. FERC ("NRG").

In a 2011 filing made under Section 205 of the Federal Power Act ("FPA"), MISO proposed significant revisions to its resource adequacy requirements ("2011 Filing"), which FERC conditionally accepted in 2012, and again on rehearing in 2015. In those orders, FERC largely approved of MISO's resource adequacy proposal, but conditioned its acceptance subject to certain revisions, namely, that MISO strike

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from