FERC Proposes Revisions To Geomagnetic Disturbance Reliability Standard

On May 17, 2018, FERC issued a Notice of Proposed Rulemaking ("NOPR") in which it proposed to approve Reliability Standard TPL-007-2 (Transmission System Planned Performance for Geomagnetic Disturbance Events) ...

United StatesEnergy and Natural Resources

On May 17, 2018, FERC issued a Notice of Proposed Rulemaking ("NOPR") in which it proposed to approve Reliability Standard TPL-007-2 (Transmission System Planned Performance for Geomagnetic Disturbance Events) submitted by the North American Electric Corporation ("NERC").  Geomagnetic disturbance ("GMD") events result from charged particles ejected from the sun that interact with and cause changes in the earth's magnetic fields, impacting flows on electric power systems and potentially causing voltage instability and equipment failure.

NERC submitted the proposed Reliability Standard TPL-007-2 for approval in response to a Commission directive in Order No. 830.  Order No. 830 directed NERC to modify the previously-effective GMD Reliability Standard TPL-007-1 (Transmission System Planned Performance for Geomagnetic Disturbance Events) to: (1) to revise the benchmark GMD event definition, regarding the required GMD Vulnerability Assessments and transformer thermal

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.