FERC Partially Grants CAISO Waiver Of Aliso Canyon Related Tariff Provisions

On November 26, 2018, FERC partially granted the California Independent System Operator Corp. ("CAISO") a temporary extension of two sets of tariff provisions concerning natural gas system limitations

United StatesEnergy and Natural Resources

On November 26, 2018, FERC partially granted the California Independent System Operator Corp. ("CAISO") a temporary extension of two sets of tariff provisions concerning natural gas system limitations on CAISO's system and corresponding market operations. While FERC temporarily extended six tariff provisions related to the Aliso Canyon gas storage facility ("Aliso Canyon") effective November 30, 2018, and December 16, 2018, as requested, it rejected CAISO's proposal to temporarily extend the tariff revisions regarding gas price scalars.

In June 2016, FERC first accepted proposed tariff revisions from CAISO in response to a large natural gas leak that occurred at Aliso Canyon in October 2015 (see December 6, 2017 edition of the WER). The tariff revisions established market measures, on an interim basis, to address the reliability and system operational risks presented by the Aliso Canyon event. In November 2016, FERC accepted CAISO's proposal to extend

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from