On September 6, 2018, FERC mostly denied rehearing of its
February 20, 2018 order ("Proposal Order") that accepted
PJM Interconnection, L.L.C.'s ("PJM") proposal to
reduce the number of bidding points at which virtual transactions
may be submitted by market participants ("Virtual Transactions
Proposal"), finding PJM's Virtual Transactions Proposal
just and reasonable. However, FERC did grant rehearing with respect
to PJM's request to modify the effective date of the revisions
accepted in the Proposal Order to February 22, 2018.
In the Proposal Order, FERC approved PJM's Virtual
Transactions Proposal to, among other things, (1) eliminate
biddable points at zone nodes, certain generator nodes, certain
aggregate nodes, and individual load zones for Increment Offers
("INCs") and Decrement Bids ("DECs") and
instead align the eligible trading points for INCs and DECs with
nodes where generation, load, or interchange transactions are
settled, or at trading hubs where