ARTICLE · 30 MAY 2018

FERC Limits Analysis Of Upstream/Downstream Impacts Of Proposed Gas Pipeline Projects

On May 18, 2018, FERC denied rehearing of its April 28, 2016 order (the "April 28 Order") approving Dominion Transmission, Inc.'s ("Dominion") New Market Project.

United StatesEnergy and Natural Resources

On May 18, 2018, FERC denied rehearing of its April 28, 2016 order (the "April 28 Order") approving Dominion Transmission, Inc.'s ("Dominion") New Market Project. Notably, FERC held that it is not required to analyze the upstream and downstream impacts of a proposed pipeline project unless those impacts are considered cumulative or indirect effects within the meaning of the National Environmental Policy Act ("NEPA"). Commissioners Cheryl LaFleur and Richard Glick dissented in part, instead finding that FERC is required to provide the public with information relating to the upstream and downstream impacts of a proposed project and stating that FERC should ask applicants to provide such information.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from