FERC Lacks Jurisdiction To Set Station Power Charges

On December 18, 2012, the U.S. Court of Appeals for the District of Columbia Circuit issued its ruling in Calpine Corp. v. FERC and affirmed FERC’s conclusion that it does not have the authority to regulate public-utility charges to independent generators for the generators’ use of station power.

United StatesEnergy and Natural Resources

On December 18, 2012, the U.S. Court of Appeals for the District of Columbia Circuit issued its ruling in Calpine Corp. v. FERC and affirmed FERC's conclusion that it does not have the authority to regulate public-utility charges to independent generators for the generators' use of station power.1 The D.C. Circuit agreed with FERC that such sales are retail sales of power that are subject to retail jurisdiction. That jurisdiction extends to the question of whether or not a sale of retail power has occurred.

After Order No. 888 unbundled generating from transmission and distribution services, the issue of how independent generators would be charged for station power arose. FERC created "netting intervals," under which a generator is not required to pay retail rates for power consumption as long as its net output is zero or positive over a fixed period. If the generator uses more power than it sends to the grid, it is considered to have obtained the shortfall in a

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from