ARTICLE · 24 DECEMBER 2025

FERC Issues Order Providing Guidance For "Co-Locating" Power Plants With Data Centers Within PJM

Baker Botts L.L.P.
Baker Botts L.L.P.
Contributor
Baker Botts L.L.P.

Baker Botts L.L.P.

Baker Botts is a leading international law firm with 11 offices located in the US, Europe, and the...

View firm profile
Explore more from Baker Botts L.L.P.

Commission directs PJM to provide new types of transmission service designed to "facilitate more rapid interconnection and operation of Co-located Loads"

United StatesEnergy and Natural Resources

Commission directs PJM to provide new types of transmission service designedto "facilitate more rapid interconnection and operation of Co-located Loads"

On December 18, 2025, the Federal Energy Regulatory Commission ("Commission" or "FERC") issued its order in the show cause proceeding1 ("Co-Location Order" or "Order") to address issues associated with large loads (e.g., AI-driven data centers) co-located at generating facilities in the PJM Interconnection, L.L.C. ("PJM") footprint.2 To reduce grid costs and enable faster interconnection of co-located large loads and generators, the Commission directs PJM to offer new types of transmission service based on a large load's net withdrawals from the system, as opposed to requiring co-located loads to be served by traditional front-of-the-meter network transmission service. These new transmission service options—Firm and Non-Firm Contract Demand Service—will reduce the scope of required transmission upgrades thereby

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from