Commission directs PJM to provide new types of transmission
service designedto "facilitate more rapid interconnection and
operation of Co-located Loads"
On December 18, 2025, the Federal Energy Regulatory Commission
("Commission" or "FERC") issued its order in
the show cause proceeding1 ("Co-Location
Order" or "Order") to address issues associated with
large loads (e.g., AI-driven data centers) co-located at generating
facilities in the PJM Interconnection, L.L.C. ("PJM")
footprint.2 To reduce grid costs and enable faster
interconnection of co-located large loads and generators, the
Commission directs PJM to offer new types of transmission service
based on a large load's net withdrawals from the
system, as opposed to requiring co-located loads to be served by
traditional front-of-the-meter network transmission service. These
new transmission service options—Firm and Non-Firm Contract
Demand Service—will reduce the scope of required transmission
upgrades thereby