FERC Issues Further Guidance Regarding Transmission Cost Allocation and Planning: Much More Remains Unresolved

Mayer Brown
Mayer Brown
Contributor
Mayer Brown

Mayer Brown

Mayer Brown is a leading international law firm positioned to represent the world’s major...

View firm profile
Explore more from Mayer Brown

The US Federal Energy Regulatory Commission (FERC) and the electric industry continue to struggle with the issue of who should bear the costs of transmission upgrades and how related planning should be handled.

United StatesEnergy and Natural Resources

Originally published July 27, 2010

Keywords: FERC, transmissions cost allocation, electric industry

The US Federal Energy Regulatory Commission (FERC) and the electric industry continue to struggle with the issue of who should bear the costs of transmission upgrades and how related planning should be handled. A recent FERC filing addresses one set of proposals, while another recent filing sets the stage for further action.

In two related, recent FERC orders¹ accepting tariff revisions by Southwest Power Pool, Inc. (SPP), FERC has provided additional guidance regarding transmission cost allocation and planning following FERC's related recent notice of proposed rulemaking.²

In the Cost Allocation Order, FERC permits SPP to adopt the so-called "Highway/Byway Methodology" and to allocate related transmission costs for certain transmission projects³ based on the related voltage, as follows: