As power demand surges, on December 18, 2025, the Federal Energy Regulatory Commission ("FERC" or "Commission") announced a much-anticipated order laying the groundwork for new rules governing the co-location of large loads alongside electric generation in the Pennsylvania-New Jersey-Maryland ("PJM") region

United StatesEnergy and Natural Resources

As power demand surges, on December 18, 2025, the Federal Energy Regulatory Commission ("FERC" or "Commission") announced a much-anticipated order laying the groundwork for new rules governing the co-location of large loads alongside electric generation in the Pennsylvania-New Jersey-Maryland ("PJM") region.

FERC defines "co-located load" as "end-use customer load that is physically connected to the facilities of an existing or planned [generator] on the [generator's] side of the Point of Interconnection." While the order applies to any co-location arrangement, as the Commission news release stated, its intent is to "facilitate service of AI-driven data centers and other large loads."

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from