FERC Holds Technical Conference On Local Transmission Planning Issues In CAISO Amid Concerns Of Order No. 890 Compliance

On May 1, 2018, FERC staff held a technical conference on local transmission planning within the California Independent System Operator Corporation ("CAISO") footprint.

United StatesEnergy and Natural Resources

On May 1, 2018, FERC staff held a technical conference on local transmission planning within the California Independent System Operator Corporation ("CAISO") footprint. The conference comes at a time when two California utilities, Pacific Gas and Electric Company ("PG&E") and Southern California Edison Company ("SCE"), have transmission planning issues before the Commission, and also following FERC's recent order addressing compliance with Order No. 890 in the PJM Interconnection, L.L.C. ("PJM") region (see February 20, 2018 edition of the WER).

Beginning in 2007, FERC issued Order No. 890 and several follow-on orders to increase nondiscriminatory access to the transmission system and eliminate artificial barriers to entry and participation by stakeholders. A key component of the Order No. 890 series is the requirement that transmission providers establish planning processes that satisfy various planning principles. In these orders, FERC explained that Regional

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from