Share on LinkedInShare on LinkedIn

ARTICLE · 18 OCTOBER 2016

FERC Grants Second SPP Waiver Request To Permit Payment Plan For Eight-Year Backlog Of Transmission Revenue Credits

On September 30, 2016, FERC granted a Southwest Power Pool, Inc. ("SPP") petition for waiver of certain provisions of the SPP Open Access Transmission Tariff ("Tariff") in order to provide the option...

United StatesEnergy and Natural Resources

On September 30, 2016, FERC granted a Southwest Power Pool, Inc. ("SPP") petition for waiver of certain provisions of the SPP Open Access Transmission Tariff ("Tariff") in order to provide the option of a payment plan to entities affected by SPP's delayed implementation of a revenue crediting process for transmission upgrades.

Under Attachment Z2 of the SPP Tariff, transmission customers paying for directly assigned network upgrades can recover their costs, with interest, from customers taking new transmission service that could not have been provided "but for" those network upgrades. On April 1, 2016, SPP filed a request for waiver of several provisions of its Tariff in order to implement the Attachment Z2 revenue crediting process. In its petition, SPP stated that it had been delayed since 2008 in implementing revenue crediting due to, among other things, numerous delays associated with developing and deploying the necessary software. SPP stated that it anticipated

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from